The following tentative schedule identifies the approach the MCPD will take in screating a new Park District Master Plan.  The Schedule is subject to change as circumstances dictate or as determined necessary by or in the best interest of the MCPD.

 

RFP is Released                                              March 6, 2018  Completed

Request for Proposals due                             March 23, 2018 Completed

Interviews                                                      April 10, 2018 Completed

Contract Awarded at Park Board Mtg.           April 24, 2018 Completed

P&R Master Plan Study                                  May 2018 - September 2018

Final Plan Presented to the Board                 October 9, 2018

 

RFP, Supporting Documents & Links

Request for Proposal Document

Comprehensive Site Plan Yunker Farm Park -Advisory Committee – 2002

Mokena Community Park District Comprehensive Master Plan 1995

Mokena Community Park District Comprehensive Master Plan 2005 

Mokena Community Park District Master Plan Update - 2010

Mokena Downtown TIF District Plan - December 2008

Mokena, Illinois Master Plan - August 2002